It was over 6 weeks since the builders were last on site and I was becoming very concerned about the delays which were occurring. This day they positioned the main concrete beams onto the columns that they put in place 6 weeks previously, that will eventually take the weight of the whole house.
I know the beams had to be fabricated off-site in a precast concrete factory which required a certain lead-time but the builder had all of the dimensions etc right at the beginning of the project and did all of the stress and weight calculations themselves. So they could have placed the order in early March, and perhaps they did for all I know, so as I am not aware of the lead-time required for items such as these, for now I will give them the benefit of the doubt.
I’ve got another couple of videos in the pipeline but have been in no hurry to publish them precisely because progress has been so slow in the meantime. The fact is that all of the materials to run the services and utilities to and from the property have been on site (and paid for by me) for several weeks but the builders have been dragging their feet to actually do the work to the point that it’s now almost approaching becoming a dispute between us. More details will be provided in future videos.