Plumber finished

For now at least. He didn’t connect the heat pump pipes either inside or outside and left the WC in the bathroom unconnected as that’s got to come out for the tiles to be rectified, but he did connect everything else up and also made a temporary connection to the mains supply to test the system out. Here’s the heat pump exterior heat exchanger. The water pipes are unconnected and for now the hole is still open in the wall.

null

null

null

Here’s the temporary mains connection. Unfortunately it means that for now there isn’t a connection for a hosepipe but I shouldn’t be needing one over the week-end as I’ll be working on installing the kitchen.

null

Here’s the little handbasin in the separate toilet. The mixer tap that the builder supplied was much larger than the one I bought for the bathroom washbasin and when I showed it to the plumber he said he’d swap them for me, which he has done.

null

null

I turned the tap on and water came out of it and the WC also flushed but before leaving the plumber had turned the main stopcock off and the flow stopped. I didn’t want to turn it back on again just in case there’s something to do with the heat pump supply that I don’t know about.

Here’s a general view of the utility room now all of the connections bar the ones for the heat pump have been made. I understand why the manifold has been used to connect up the hot and cold water system but I can’t say that I find it very pretty and I think it also takes up a lot of space.

null

This is the arrangement in the corner for a waste for the sink I intend to install in the future and a washer/dryer and the cold supply for the latter. When I get into the house and get the chance I’m going to try and find a way to modify it so it protrudes less from the wall.

null

This is the hot and cold water system manifold.

null

Here’s a final shot of the connections above the heat pump system unit. It’ll be a nightmare trying to paint the walls with that lot in the way. I wish I could have done it previously but I had no idea that the unit would be that big.

null

This is a shot of the heat pump pipes in the corner of the wardrobe alcove in bedroom 2. The plumber has boxed them in from floor to ceiling which was a good idea and makes for a neat job.

null

I did a reasonable amount of work myself today assembling all of the wall cabinets ready for when I can mount them on the kitchen walls.

null

null

I finished off by getting the first floor mounted cabinet ready to be installed and also drew the first line on the wall to align all of the floor cabinet tops to, but I’ll leave that until later.

More plumbing and kitchen

The plumber turned up again and when I said that he’d never get finished today, as was the original plan, he said that he’d be back again tomorrow. As I thought I might be continuing to work in the kitchen I moved all of the flat-packs out of the bedroom where I’d stored them into the living room and kitchen as I knew he’d be walking up and down the corridor connecting up the heat pump and I didn’t want to get in his way.

As it happens, I didn’t do any work at all in the house today because afterwards I decided to check the prices and availability of the kitchen equipment that I decided to go for a few weeks ago. I was shocked to find by how much many items had increased in price. I had originally spent ages looking for a range of the same brand to install in the kitchen and I didn’t much fancy doing the whole exercise again.

But I didn’t have to, because when I checked the prices of other manufacturers’ items they had also gone up in price by at least the same amount, and some by a lot more. I’d chosen to go for Indesit products, not because I’m an especially great fan but because they are the ONLY manufacturer offering a free-standing fridge of a suitable height for my kitchen layout – 142 centimetres. So the exercise became all about searching again for the most competitive suppliers of the items I want and biting the bullet when prices of some (most) of them had increased in the meantime.

Given the upward price trend, there seemed to me to be no point in not buying the items that I need now, especially now the floor is down in the house and they can be stored in the living room when they arrive. So I ordered a hot plate, a dishwasher (ouch!), a fridge and an oven. The hot plate and the dishwasher will be delivered in a few days time but the fridge and the oven I ordered to be picked up from local stores, the fridge from Conforama in Périgueux and the oven from Electro Depot in Brive.

The fridge also will not be available for a few days but the oven was available for pick up today, so that’s what I decided to do come late afternoon after I’d got all of the purchases organised. I have to say, the Electro Depot ‘drive’ system worked incredibly well.

They sent a text message for me to confirm when I’d be arriving to pick the item up with a link for me to click on arrival adding which parking bay I’d be in. I then went to the door and within a minute or so a young lady arrived wheeling a parcel on a trolley. I asked her which bay she was going to and she told me ‘number 3’. That’s me I said and she gave me a hand to load it into my car. Great system.

I checked what the plumber had been up to while I’d been gone, starting with the exterior heat pump unit that’s now attached, but not connected, on the house’s northern wall.

null

null

Next was the corner handbasin in the separate toilet. I think that the mixer tap that I bought from the same manufacturer for the main hand basin in the bathroom could be slightly smaller than the one the builder has supplied but I’ll have to check. If so, I’ll probably end up swapping them over as the mechanism for operating the plug on this one is a bit too tight against the wall.

null

null

I notice that the plumber had cut the pipe off that’s now no longer needed for the external tap. It looks rather unsightly but it probably won’t look too bad when I’ve filled the hole and topped it off with brilliant white grout. I’ll know not to make the mistake again in my next lifetime when I decide to design and build another house…

Now the WC in the little toilet. I’m appalled by the huge vent coming out of the floor next to the toilet itself but there’s nothing I can do about it. The current regulations say that you must have secondary air inlets for the waste pipes going into the ‘fosse septique’.

The alternative would have been to have huge pipes going right up the wall, out through the ceiling and joining in the roof space to connect to an external roof air inlet, which would have looked even worse than it does now. I just wish that white plastic tubing had been used though rather than the hideous dark grey stuff that is now in full view 🙁

null

null

Similar comments to the above apply for the WC in the bathroom. Although it appears to be in the following shot, the WC hasn’t been fixed to the wall and floor. That’s because it will have to come out again to allow the dark tiles to be removed and replaced.

null

Here’s the shower unit, connected up but not usable until the mosaic floor tiles have been laid and the outlet made good.

null

Now a couple of shots of the heat pump unit nearly fully installed in the utility room. As can be seen, the plumbing on and around it is quite complex and my big regret is that I didn’t paint the walls and ceiling in there the same as I did in the kitchen. It’ll be impossible to do them properly now and if there’s one thing that I detest, it’s visible unpainted plasterboard walls 😐

null

null

The exterior heat pump connections will be punched through from outside into the back corner of the alcove in bedroom two in which there will be a built-in cupboard. That hasn’t been done yet as can be seen in the next shot.

null

Finally, the Indesit oven that I picked up this afternoon from Brive. More about that when I come to install it.

null

The final upside to the day – there’s a cherry orchard just the other side of Terrasson that sells the most delicious dark red cherries. I’ve been there a few times since I came to France but not since Covid and today was the first opportunity I’ve had to drop in again. And lucky actually, as the season will soon be over.

I treated myself to 2 kilos at 6€ a kilo, half the supermarket price and twice the quality. I’ll make a pig of myself for a few days and probably end up regretting it when I put on weight. But you’ve got to have some pleasures in life, haven’t you 😉

Coming along

The plumber didn’t show up today so there’s no way he’ll be able to finish his work by tomorrow, which he’d said was the plan. So yet again I’m in the dark as to what’s going on behind the scenes.

I had a couple of issues to deal with, therefore, this morning but after an early lunch I went straight up to start assembling the kitchen units. I started with the base units, of course, and I have to say that I’m very impressed so far with this new Brico Depot kit. It took me a short while to get the hang of the first unit I did but they all use the same principles and as time went on I was putting them together at great speed with no mistakes.

I’ve only put the shells together for now to see how they go into the kitchen space and I’m relieved to say that there were no nasty surprises. Everything fits into where it’s supposed to go although I’ll have to cut a slot in the back of the right hand corner unit where the pipe is for the outside tap, an access hole for the tap for the dishwasher and an access hole in the back of the sink unit for the services in that area, none of which is unexpected or difficult.

I finished at around 6.45 pm and here’s how things looked when I was about to leave.

null

null

null

null

null

All being well, I expect to press on with the kitchen tomorrow and hope to make more good progress, even getting to the point that the units are in and fixed to the wall. I was thinking about painting the shutters this week as the weather is so hot and dry but I think it’s better to concentrate on the kitchen while there’s no tradesman working inside the house, like today.

They just keep coming

Problems that is. Ones that are totally unnecessary and wholly avoidable.

Over the week-end after the tiler had cleared up and gone (hardly ‘cleared up’ actually as yet again it was left to me to clear away the rubbish and mess that had been left behind) I took a first proper look at the work that had been done. I was really pleased with the tiling in the little toilet but as soon as I entered the bathroom I was shocked by the sight that met my eyes.

A large area of the main wall that had been tiled was of a different shade of white to the rest. Almost half of the lower section together with another tile in the top left corner and yet another half way up the adjacent wall were of a much darker tint and the difference was so great as to be unignorable. Even if no more dark tiles were used in the rest of the room, as far as I was concerned the room was ruined.

The next few photos give an indication of the problem but the difference in tint is far more striking in reality than in the pictures.

null

null

null

null

I know what has happened. Tiles from two different manufacturing batches have been combined on the same wall. Anyone who knows anything about tiling, and a pro especially, knows that you should always avoid doing that and especially for tiles that are brilliant white. That’s why I bought a large number of tiles all at the same time rather than room by room.

I think I know what happened. All of the tiles originally came in white cartons and were, I suspect, from the same batch. However, when I asked Leroy Merlin to replace two cartons the contents of which were damaged, the replacements came in brown cartons and were almost certainly from a different batch. Instead of the pro putting these to one side and using up all the tiles in the white cartons first, they used the ones in the brown cartons part way through in the middle of the job.

I cannot believe that a pro should have to be told about this. I would never have done it and such a stupid error was totally avoidable as there’s a large number of tiles in white cartons still available. As it is the dark tiles will have to be removed which would have been easy if it had been done immediately the difference became apparent and the adhesive hadn’t cured. Now it will be much more difficult and to make matters worse, the plumber arrived today.

As agreed, he has finished in the kitchen and although he has agreed to leave the bathroom until last, he has capped off the connections to the bathroom hand-basin but will be unable to install the WC until the tile problem has been rectified. I have contacted the builder and the tiler about the problem but so far the tiler has not replied. If it means that the plumber is unable to install the toilet before Thursday when he is due to finish he’ll have to come back later because I am not going to live with an unsightly two-tone bathroom. By the way, the plumber agrees with me.

Here are today’s plumbing photographs starting with the two outside taps, which look great. This is the one at the rear.

null

Here’s the one at the front. The plumber questioned why I wanted it right up front on the angle of the house where it was going to be in full view and he also said that the supply for it would be an eyesore in the corner of the little toilet as you’ll see in a moment. He suggested that it would be better just to remove the supply pipe in the toilet and use another further along outside the utility room which he just happened to have installed when he did the initial plumbing work.

He was absolutely right of course, and here’s the front tap in the position that he recommended.

null

Here’s what he meant about the supply pipe in the toilet. He’s right, it would need a stop-cock on it and to be extended (see the kitchen below) and would have been a total eyesore. It’ll just have to be cut off and grouted over and if I can replace the tile later (which I doubt) that’ll be a bonus. Even if it’s just disguised it’ll be preferable to having the supply pipe in there and I have only myself to blame.

null

Next the kitchen. Notice the supply pipe for the rear outside tap and how it has to have a stopcock on it (a ball valve actually) which would have looked awful next to the small hand basin in the little toilet. It doesn’t matter in the kitchen though, because the whole arrangement will be hidden behind a kitchen unit and made accessible through a removable panel.

null

Now other stuff. Here’s the manifold now connected up for the underfloor heating. Standing next to it is the exterior heat pump unit which will go outside against the northern wall of the house.

null

This manifold in the utility room hasn’t been fully connected yet. It’s for the house’s hot and cold water system and seems to me to be very complicated seeing as it’s only for four rooms – the bathroom, kitchen, utility room and separate toilet. Next to it is the stopcock for the house’s main supply.

null

Here’s a closer shot of the main stopcock. It’s a pity that this whole setup takes up so much space and is so far off the wall.

null

The same can be said for this arrangement in the corner of the utility room. It’s for a hot and cold supply to a small sink when I can get around to putting it in and also for a washer/dryer. He’s used rather large shut-off valves for both this and the dishwasher in the kitchen – I found smaller, nicer looking ones for my old house.

If you notice, he’s also put the waste pipe for the sink to the left of the waste for the washer/dryer. This is not the arrangement I would have preferred because it means that the waste pipes will cross over bringing them further off the wall than necessary and causing the washer/dryer to stand further out into the room from below the worktop.

null

Finally a shot of the heat pump unit that will stand in the corner of the utility room. It’s much bigger than I thought it would be and I’ve also noticed something else. It has a thick electrical connecting cable and there’s no plug point in that corner of the room. Hopefully the electrician has another suitable arrangement in mind 😕

null

Taking it easy today

Yet again I’ve worked non-stop for several days so I’m going to take it a bit easy today and just cut the grass. If that can be called ‘taking it easy’…

Incidentally, I’ve done a quick calculation and I think that the total area of the walls and ceiling in the kitchen is about 49 sq. metres meaning that according to the tin, I used almost exactly twice as much paint on them as I should have done.

Looking at it another way, the spray machine makes it easy to apply a lot more paint than you realise, because unlike hand painting or rolling, it’s almost effortless. So in future I really must make sure that I take it more easy with the spraying as otherwise decorating the house will become a very expensive exercise 😐

Spraymazing!

First I had to mask up the kitchen window and the second doorway. The latter I did by masking it from the inside, cutting a slit in the middle to about half-doorway height and then adding a curtain covering the slit. I also had to add a band of masking across the bottom of the doorway to make the barrier more impervious. Then I had to get the spraying machine ready to go, which is when the fun began.

I had no idea how its controls actually worked aside from the very brief comments contained in the laughably entitled ‘user manual’. Having dipped the delivery tube into a bucket of water I aimed the gun outside towards an old sheet of polythene and pulled the trigger. What eventually came out was a solid jet of water, hardly what I expected or wanted.

I thought that maybe the machine required a more viscous medium to work so placed the delivery tube into a can of sealing undercoat and tried again. Same result. I’d wasted at least a litre or so of paint (probably more) before I decided that I needed to find out what was wrong with the jet. There was a jet that came with the machine in a separate container that, from the wording, sounded like a second ‘alternative’ jet so I decided that I’d do a swap and try it out.

To cut a long story short, it turned out that this was the ONLY jet and it needed to be installed in the machine as at the time of delivery no jet is actually fitted. I guess it would have been a nice idea to have mentioned this in the ‘user manual’ with clear instructions on how to install it but apparently the manufacturer thinks otherwise.

When I’d eventually got it into place (and cleared up the mess) it turned out that the machine worked amazingly well and after I’d realised that I hadn’t got a mask on, stopped and resumed spraying after donning my brand new 3M ‘masque de protection respiratoire’ it actually only took me a matter of minutes to spray all of the walls and ceiling in the kitchen.

null

null

Here’s after I’d removed all of the masking film from the floor. That was a blessed relief as there was a lot of plaster dust on its surface which until then had been walking in and out of the kitchen onto the floor tiles in the living room.

null

null

null

null

Some shots of the ceiling.

null

null

null

Here are the plumbing pipes after I’d removed their masking ready for when the plumber comes in.

null

Cleaning the machine took several times longer than it did to spray the whole kitchen, so the lesson is to get as much spraying of the same colour as possible lined up to do all at the same time. I was also surprised how much paint I used. I opened a new 12 litre can of paint and by the time I’d finished, the delivery tube was drawing in the last drops.

Let’s say that given what was left and the amount I’d wasted getting the machine running I’d used 10 litres. That’s enough, according to the can, to cover 100 sq metres. I haven’t done the sums but that seems like quite a lot for the size of the kitchen. Maybe I’ll have to be more sparing in my spraying efforts in future.

I’ve left masking tape around the doorways, window and floors because the walls and ceiling will have to be painted after the plumber has finished. I’ll have to re-mask the walls, window, doorways and floor to do the ceiling (in white) and the ceiling and coving when I do the wall sections that will not be tiled, but that’ll be a comparative doddle without all the plaster dust that there was previously.

Not a lot to show

I finished at around 6.30 pm because my back was killing me. I’d done a good few hours work but wanted to go on for longer and get the kitchen walls and ceiling sprayed with sealing undercoat but that was not to be.

Even so, I did get quite a bit done. The walls and ceiling have all now been rubbed down and wiped with a damp cloth to remove excess plaster dust, so they’re now ready for painting. It’s the masking up that’s taken the time – and the final bit of rubbing down near floor level that killed my back.

I’ve masked up one doorway and cleaned around the window frame so that’s also ready for masking. I’ve got to mask the other doorway though, but in a way that allows me get in and out while the paint sprayer is running so I can leave it outside the room but be able to turn it on and off.

null

null

The machine itself took a bit of assembling. Like most Chinese instruction manuals, it was as clear as mud. The problem was attaching a circlip to hold the paint inlet tube on – the instructions just said to do it without saying how. I managed it after bending its ears slightly because they were touching before the circlip could be made small enough to even begin to enter its groove, but I finally managed it.

null

So by the look of it, I should get the kitchen walls and ceiling painted tomorrow. The amount of dust generated by rubbing down the plaster has been the main bugbear with enough being present to make sticking the masking tape to the surfaces to be masked challenging to say the least. Luckily I did the walls and ceilings in the living room and corridor before the tiles went down and if I did it again, I’d do the same in every room. Too late now though 🙁

I’ve not done this before

Not on a house anyway. I’ve used sheets of the film that’s used to mask up cars for painting to mask up my kitchen floor prior to rubbing down the ceiling and wall plasterwork. I’m not too worried about some dry plaster dust falling onto the tiles as it’ll brush off but I want to catch the worst of it and also protect the floor when I spray the ceiling, coving and tops of the walls with sealing undercoat.

null

null

null

null

This is what it’s all about. As I found when I did the ceiling and walls in the living room and corridor before the floor tiles were laid, just a little rubbing down creates an awful lot of plaster dust.

null

null

Tomorrow I’ll wipe the ceiling, coving and wall tops with a damp rag and when it’s dry use my ‘pulverisateur’ airless sprayer to give them a coat of sealing undercoat. I haven’t yet decided whether to try doing all of the walls because that would need the dust to be removed without damaging the film and creating a mess and for the masking to be securely attached all around to protect the floor tiles. I’ll have to see how things go.

Tiling done!

Not quite, but the tiler did what I asked him to, which was everything that was necessary to allow the plumbing work to go ahead, starting with the kitchen. More actually, because as well as doing all of the floor, he totally completed the tiling of the small toilet and just left one wall to be tiled in the bathroom, which he’ll be able to do when he returns to do the shower area.

Here are the pictures, which are mostly self-explanatory.

null

null

null

Looking towards the entrance of the separate toilet.

null

Here are a couple of shots of two walls inside the toilet showing the two rows of ‘wave’ pattern tiles that break up the plain white. Exactly the same theme appears in the bathroom and will also be above the worktops in the kitchen and utility room.

null

null

The kitchen. As can be seen, I told the tiler that he didn’t have to fit plinths beyond the ends of the two walls where there will be appliances – fridge near the opening door and dishwasher near the opening into the living room. There was no point as the rest of the walls will be covered by fixed furniture units and will therefore be invisible. He has left behind a lot of plinths and floor tiles anyway which will be available in the future should they be required for any reason.

null

null

The utility room. Although much of the plinths along the wall where the pipes are will be covered by fixed furniture units, that could be several months away so in the meantime it will be better for the plinths to be in place as they will be visible.

null

The bathroom.

null

null

null

Because the house is in a ‘V’ shape there has to be a change in direction of the floor tiles where the two arms of the ‘V’ join. Here’s a shot of where the living room joins the corridor outside the kitchen door.

null

Here’s a shot of the entrance into the separate toilet. In theory the living room tiles could have been continued into it but we decided that having floor tiles that were diagonal to the walls rather than parallel would have been an eyesore.

null

So that’s it, the plumber can now come in any time and hopefully soon. In the meantime I’ve now got a huge amount to do – painting the ceiling in the living room and corridor, painting the ceiling and walls in the kitchen, assembling and fitting out the kitchen, removing and painting the shutters, replacing the exterior hold-back clips for the living room double door shutters, laying the bedroom floors, painting the ceilings in all of the other rooms… and that’s just for starters. But know what? Now we’re getting there I’m really looking forward to it 😀

More tiling

The tiling team were back on site bright and early to continue the floor tiling. They don’t say much, especially the two younger members of the team, they just press on and get the work done.

null

null

They will continue on to tile the walls in the bathroom and separate toilet and work had indeed started on the latter by mid-afternoon which came as a surprise to me.

null

The walls in the bathroom were prepared for tiling earlier in the day with the walk-in shower corner having been specially treated to make it completely waterproof. Unfortunately I didn’t get any shots when I had the chance and I didn’t want to enter the house later after they’d left for the day. I also don’t know if the small toilet was fully completed for the same reason.

null

null

null

null

null

Didier, the builder’s clerk of works, turned up this afternoon and it was formally agreed that when the tilers have finished and the plumber can come in to start their work, the latter would complete the plumbing in the kitchen before starting work in other areas of the house so I can start the installation of the kitchen units. I also impressed the importance of the house being ready for occupation before August and I was reassured that this would definitely be the case 😐

Well pleased

When I looked out of my caravan at around 8.45 am all was quiet up at the house and the tiles that had been stacked outside at the rear were still there, so I thought that nothing was happening. I’d already been up there at around 7.00 am and had opened as many windows and doors as I could (I still couldn’t open the double doors in the living room because the builder still had the keys) to let some cool air inside because it was quite warm in there with the shutters having been left open for several days.

So I was pleasantly surprised when I was driving out shortly after 9.30 am to collect the paint for the shutters that had been delivered to a ‘point relais’ in Montignac to find that the tilers had arrived and had already started work some time before. When I looked inside the interior was filled with a thick cloud of dust and the boss asked if I had the keys to the living room doors. I didn’t, of course, because the builder had them and hadn’t thought to issue them to the tilers who were rather put out, so the builder had shot themselves in the foot.

After I’d picked up the paint I went inside to check on progress and was pleased to see that a waterproof area had ben laid for the shower even though the mosaic tiles for it are not yet available and a good start had been made in the living room.

null

null

null

Things had moved on quite a bit more when I looked in again in the early afternoon.

null

null

I looked back in at around 5.00 pm just before they finished for the day and took some final shots. I didn’t want to go into the house after they’d gone in case I did any damage to the floor even though they said that the floor could take weight after only a very brief delay and were walking on it themselves.

null

null

null

They will not have finished the corridor today and the bathroom and ‘cellier’ floors are still to do. This morning I gave the boss a copy of my tiling plan for the bathroom so I’m also looking forward to finding out tomorrow what the deal will be for them to tile all of the walls in there and also the separate toilet.

Mission accomplished

I got the coving up in the kitchen this morning. It took about 3 hours, a bit longer than the other rooms, but that was because of the complexity of its shape.

null

null

null

null

It’s been a very hard few days but at least the job is now done and the interior is clean and tidy and ready for when the tilers come tomorrow, hopefully, to lay the floor tiles. The effort should be worth it though as after all the delays, I’ve got to do everything I can to help bring forward the date when I can finally move in.

3 out of 4

I was up at around 6.00 am this morning and after I’d had a leisurely breakfast and emptied my bins I was up ‘on site’ getting things ready to start work by about 8.00 am. The two ceiling coving priorities were the bathroom and the separate toilet because let’s say, unlikely though it’ll be, that I can agree a price with the tiler and he says that he can continue non-stop with the wall tiles after doing the floor, as both of these rooms will have floor-to-ceiling wall tiles the coving will have to be already in place for him to tile up to.

So I started on the bathroom first, which took about 2 1/2 hours to do.

null

null

I was then going to move on to the separate toilet but as I was on my last cartridge of adhesive, I decided that it would be a good idea to get some more so I can work tomorrow. I checked on the internet and found that Bricomarché at Le Bugue had what I needed at a cheaper price than Leroy Merlin so I saved a lot of time by going there. When I returned I had a very quick lunch and resumed work on the separate toilet.

null

null

By the time I’d done that it was still only mid-afternoon so plenty of time to get cracking on the ‘cellier’ (the utility room). Despite there being some tricky trimming to do around the electric utility box it was all done and dusted by about 5.30 pm.

null

null

As can be seen in the final shot above, the plasterers didn’t make good the corner of the ‘cellier’ next to the electrical service. I’ll just do it myself to save time as that part of the room will be painted and the corner will therefore have to be tidied up.

But there you have it! Of the four rooms that I wanted to put coving up in, I managed to get three done and there’ll be plenty of time to just do the kitchen tomorrow. That will be a huge leap forward as only the bedrooms will be left to be done, probably after I move in. I have to say that I’m over the moon with today’s results which turned out to be much better than I originally expected 😀

Pleasantly surprised

Tired, but pleasantly surprised because today I got all of the coving up in the living room and corridor. I didn’t start until 10.30 am and finished at around 6.45 pm with just a brief stop for lunch, but I’ve exceeded my expectations. And not only that, I’m also more than happy with how the job has turned out. It’ll be well worth all the effort though, as I think it truly enhances the appearance of the interior.

null

null

null

null

null

null

null

So that leaves tomorrow and Sunday to get the bathroom, toilet, utility room and kitchen done. To be honest, if I get the first three or even two done I’ll be delighted but I’ll have to see how things work out. Although I bought more yesterday, I think I could well run out of adhesive 🙂

Good news at last

And about time! It looks as though my message about the floor tiling got through because the floor tiles that I’d been told by the builder would be delivered next week actually arrived this morning and the driver said that the tilers will be along on Monday to start laying them. These people know more about what’s going on than I do but I suppose it’s hardly surprising as they’re working and communicating together the whole time.

null

null

null

null

So by not long after 9.00 am the tiles and the adhesive were left ready for the tilers at the back of the house. I hope it doesn’t rain because if they’re going to start going in and out through the rear double doors it’ll become a mud bath that they’ll walk indoors.

null

null

null

So that left me with today, tomorrow and the week-end to get some work done myself inside the house, starting with the ceiling coving as I mentioned in my previous post. The method I use is to first fit all of the corner pieces ie two to a corner and then to finish off with straight cut pieces. The reason for that is that it can be tricky measuring out from a corner to fill a gap and it’s much easier to fill the gap with straight cuts.

The first couple of lengths were a total pain in the backside to get up and took me far too long and not only that I got into a mess with the adhesive and ended up smearing my phone and the new smart speakers that I’m using for music while I work. OK, I’m old school and this is the first time I’ve put up polystyrene coving, but even so it’s not meant to be like that.

The big problem was that it was taking ages to apply the two beads of adhesive needed on each length of coving ie wall and floor edges and I blamed my old mastic gun for that, see below.

null

And it turned out I was right to do so. I lost over 3 hours driving to Leroy Merlin to pick up a new, high tec one but it turned out to be worth it. Applying the adhesive with it became a piece of cake and needed a fraction of the time so at around 17€ it has turned out to be an excellent investment. Here it is at the end of the day. You can’t see that much because a wet rag is wrapped around the nozzle of the cartridge to keep the adhesive wet until tomorrow.

null

Like I say, I’m old school and have been used to putting up plaster coving which is tricky and difficult to get good results with, especially in the corners. So I was somewhat sceptical about this new-fangled polystyrene material and ready to turn my nose up at it. But I was wrong! Not only is it much quicker to put up but with a modicum of care, you can also get great results with it. Take a look at the corner examples below.

null

null

And here’s a straight cut joint.

null

Lovely, and that’s before going around afterwards when everything’s dry with a bit of fine filler to tidy all the joints up. After I got back from Leroy Merlin and had a quick sandwich I was able to work through with my new site lamp for a couple of hours until 9.30 pm. Seeing the amount that I got done in that time I’m pretty confident that by Monday when the tilers arrive I’ll have got all of the coving up in the living room and hall.

As I’ll probably then be unable to enter the house for at least a couple of days I’ll be looking for jobs outside. I’ll probably start stripping all of the fittings off the shutters ready for painting as the paint for them is waiting for me to pick it up and the trestles should also be along next week. I’ll probably have to move my high pressure spray machine outside as well as it’s in bedroom 3 at the moment and I’ll be unable to get to it otherwise if the floor tiles have to be left to cure for a few days.

The problems continue

I’ve just received an email from my builder saying that the floor tiles for my house will be arriving this week but that the mosaic tiles for the floor of the walk-in shower will not be available until the beginning of July. I would think that this will more likely be mid-July based on my experience to date, which poses a problem.

As I’ve explained in previous posts, until the floor tiles are down nothing more can be done inside the house – plumbing, electrical, heating – and unless work on the house restarts very soon we will end up running into August. All work will then stop and will not resume until the autumn which I’ve already told the builder will be unacceptable.

I’ve therefore suggested that the floor tiles are laid throughout the house as soon as possible but excluding the shower area. This will allow for partial tiling of the area of the bathroom wall on which the WC and washbasin are located together with the wall areas in the separate toilet on which the handbasin and WC in there are located, which will allow for all of the plumbing to be installed. This will in turn allow for the heat pump to go in and the electrical work to be completed.

I’m now waiting for a reply but while I’ve been waiting I’ve not been sitting on my hands. While no other work is going on I can be pressing on with internal work of my own, namely the ceiling coving and even the painting of the ceilings. I’ve been hampered in this by the builder playing games by taking away the keys to the double doors in the living room preventing me from opening the shutters. To overcome this and with the aim of also allowing me to work inside at any time, daytime or evening, I’ve today acquired a very useful new tool in the form of a site lamp. It’s very effective as can be seen in the following shots.

null

null

It uses high power LEDs as can be seen below.

null

I’m looking forward to trying it out by getting cracking on the ceiling coving as soon as possible this week. I’ve also got some other stuff going on. I found a supplier of very inexpensive wooden trestles and have ordered 8 of them to be delivered in a week or so’s time. These will allow me to remove the shutters from which I intend to remove all the fittings and lay them flat for spray painting using the high pressure machine that I purchased a few weeks ago.

This should make short work of them and I’ll also be using the machine to paint the interior ceilings and walls, as well as to eventually varnish the interior doors. That way I’ll not be wasting time and be getting jobs done that I’d normally have done after moving in. But the key is to get the main floor tiles down as soon as possible. I can live without a shower for a short while – after all, I’ve been in the caravan without one for two years – but I need to install the kitchen and the floors in the bedrooms so I can get all my stuff out of storage which is ticking up additional cost month by month.

My bad

The swivel clips that hold all of the house’s small shutters back against the wall when they’re open are attached to the walls below the bottom edges of the shutters, which is normal. When they fitted the clips for the shutters for the three full height double doors, the shutter men asked me if I wanted the clips below the shutters, the same as for the small ones, or on the edges.

Silly me, I should have asked what is usual, but I didn’t and after thinking about it for a few moments I told them to go ahead and fit the clips below the bottom edges. As soon as I saw the finished job I was uneasy because the clips would be very close to the ground, but I thought I could live with them.

But what I didn’t allow for was for someone who knows about these things ie Chantal, my lovely ex-neighbour from Plazac 🙂 to say as soon as she saw them that they looked silly. So that was it, they would have to be changed and today was as good a day as any to do it.

I couldn’t finish the job because the builder is playing silly buggers and has taken away the keys to the double doors making it impossible for me to open the shutters, but I could at least remove the clips today and make the holes left in the walls good and can refit them some time in the future when the builder stops playing stupid games. Here are some before and after shots.

null

null

null

null

null

null

null

While I was at it I thought I’d tackle another couple of small jobs that have been niggling me. The ‘Crépi’ gang did a good job overall but they wanted to get in and out as quickly as possible and their attention to detail left a bit to be desired.

They only applied ‘Crépi’ to the column in the front of the house down to the level of the porch which I have never thought was low enough. Obviously the ground level will be below that of the porch and the ‘Crépi’ has to go right down to ground level, which means going below it. So I decided to add some extra myself, as shown below.

null

I’ll need to decide how I’ll finish the porch off – probably with terra cotta tiles that’ll be bull-nosed along the front – but whatever I decide to do, the column ‘Crépi’ will need to go the whole way down to the ground, which it now does.

They also hadn’t been as careful as they might have been taking the ‘Crépi’ down as low as they should have in various other places around the house. It’s no big deal as I was left with two spare bags of material and later on I’ll be able to go around and patch in the high spots at my convenience. There was one small area on the front however, that was getting on my nerves and I decided to patch that today while I was at it.

null

So that was it for today, another lovely hot, sunny day. It was a bit too windy for flying so I think I made the best use of the time available by tackling the little jobs that I did do.

Shutters up

The two guys were back at around 8.00 am this morning to finish the shutter work. Just like yesterday, it was another lovely day and they made fast progress, although I’m afraid that sadly their making good doesn’t stand up to close scrutiny. Once I’ve moved in and am established in the house I may have to go behind them and make a few improvements myself as there are several places around the house where I intend to add a bit more ‘Crépi’ anyway.

They’d finished and were off by lunch time. They told me that they’d leave the shutters closed to keep the house’s interior fairly cool and when I asked they said I could open them anytime that I want. I’ll leave them for a few days before doing so, though, to allow the hinge fixings plenty of time to cure. Here are some shots of the finished job.

null

null

null

null

null

null

null

null

null

Here are some shots of the interior with all of the shutters closed. Most of the visible light is coming from the open front door.

null

I mentioned yesterday how dark it is at the bedroom end of the corridor with the bedroom shutters closed. It’ll be the same when the doors are fitted but at least then the lights will be working.

null

null

To finish off, some closer shots of the shutters themselves. If you look at the magnified versions you’ll be able to see what I mean about their making good not really being as good as it should have been.

null

null

null

null

So that’s as far as we can go for now with the external work. I suspect that the builder will leave the ‘terrassement’ (making good the ground around the house) and driveway right up until the very end. So now it’s essential for the floor tiling to go ahead before any more progress towards completion can be made. I’m hoping that that’ll be next week, but to be honest I haven’t a clue and there’s no way that I can speed it up anyway 🙁

It gets better

I knew that my hopes from yesterday had been realised when I looked out of my caravan door this morning and could see a pair of shutters leaning against the wall on the ground below the house’s kitchen window. It was also apparent from the sounds I could hear that work was going on on the front of the house.

By the time I got my drone airborne the two workmen involved had made great progress, with the shutters at the bedroom end all having been put into place and a start having been made on the full height double doors at the living room end.

null

Later on I caught them after they’d moved onto the windows at the back and it was evident that they were making great efforts getting the shutters exactly vertical and parallel to each other with identical spaces all round.

null

null

null

I went to take a closer look at the progress they’d made at the end of the afternoon.

null

null

null

null

null

The interior character of the house had been much changed by the shutters and in fact the bedrooms, bathroom and utility room were surprisingly dark with their shutters closed when I took a look inside them. Not so much the lounge, though, because the shutters on the double door at the rear still hadn’t been fitted.

null

Here are a couple of shots showing the interior locking mechanism that’s on each shutter and the locking foot that’s on the bottom of each one.

null

null

Here’s a shot of one of the gadgets attached to the wall that secure the shutters when they’re open

null

Finally, a general shot of the house’s rear.

null

They told me they’ll be back tomorrow to finish off. I haven’t looked closely yet, but obviously there’s had to be a bit of making good around the shutter hinges and fixings. I was pleased to see that they’d found the two bags of ‘Crépi’ left over from when the walls were rendered and had opened one to make sure that it matched the wall finish.

As the photos show, the shutters are in bare wood and when they’ve been fitted I’ll have the job of painting them all myself. I hope I’ll be able to take them off, lay them horizontally and use my spray-gun but I’ll have to wait and see. I certainly don’t fancy painting them all by hand 🙁