Just as Didier said it would, the new delivery of materials arrived today, just at the end of the morning. I was outside when the truck arrived and initially, before I could attract the driver’s attention, he drove into the adjacent lane leading to Labattut. He soon realised his mistake, though, as there’s no building going on down there, but as the lane is very narrow he had to reverse all the way back out again.
Here’s the truck with its legs out all ready for the delivery to commence.
First the driver had to check where there were spaces for him to drop his load onto.
His next task was to get the hook of the Hiab attached to its boom.
Then he could unload the first item, a big bag of sand.
The next item to be dropped was a pallet of Terreal beams that will be used as lintels over the tops of the doors and windows.
For reasons best known to himself he decided to find the tightest spot possible to drop them onto.
After he’d finished the delivery and gone I went up to see what the driver had left. It turned out to be just about everything that will be needed to complete the external walls.
I was very pleased to find this roll of special plastic material. There’s a pillar opposite the front door that supports the porch roof overhang which I showed as round on my plan. I noticed that the builder had changed this to rectangular and it didn’t bother me too much.
This material will be used to form the pillar that will be constructed in concrete with reinforcing steel up its centre. The material is special because it creates a pillar with a perfect shiny finish and I can’t wait to see the result.
Here’s a shot of the last item he dropped off, reinforcing steel. There are two types – one is in the form of baskets of four rods that can be cut to length and these will be placed inside the Terreal lintels and concrete poured into give them structural strength. I couldn’t work out what the pairs of rods were for and then it hit me.
When they poured the house’s concrete support columns that connect to the underlying rock all those months ago, they left rods sticking up for about a metre or so in the corners and various other positions around the walls. As they’ve progressed with building the walls, they’ve left those lengths of rod sticking up and placed special blocks with holes in over them so the rods are enclosed in the holes.
What they obviously intend to do when the walls have been brought up to their full height is drop concrete into the holes up to the full height of the walls and stick more rods in right down to the bottom. Then when the concrete has cured, the walls themselves will be anchored to the rock on which the house will be constructed. I think that is very clever.
So that’s it! Everything’s now ready for the builders to crack on with the walls which at the current rate of progress should only take a few days. The downside is that we’ve got some dismal days coming up with some daytime temperatures below freezing and occasional rain. On top of that there could be some snow towards the end of next week. The weather gods’ timing could hardly be worse 🙁