At the time of posting this it’s pretty quiet for most businesses in France that are not involved in tourism because they’re shut down for the whole of August while everyone goes off on holiday. This includes my builder so it’s a good time to do a bit of catch-up before they get back in September and, hopefully, resume work on my house.
Day 8 was actually on June 7th and although no work as such was done, it was nevertheless a big day because some important deliveries were made of materials that will be required, and for which I’d already paid I might add, for subsequent work on the house’s foundations. The following video tells the story of the morning.
The deliveries took little more than an hour but after the trucks had left, everything that would be required for the builder to complete the house’s foundations was on site ready for when they return. I also need to take the opportunity to get an expert in (what is called an ‘élagueur grimpeur’) who can climb up the large oak tree that’s closest to the north side of the house and remove the low overhanging branches that will impede construction of the walls on that side so there is no excuse for any delay in resuming the building work.